The object of the project was:
The construction of a new pumping station in the area of Agios Pavlos springs in combination with the excavation of a new well in the area and the construction of a 1429m long depression pipeline, which will lead the drilling water to a central head tank.


The construction of a head tank on the Manesi hill, with a capacity of 600m3, which will supply the external network under construction.


The construction of an external network of pipelines, with a total length of 44,057 km., In order to meet the needs of the Municipal Community of Messina, and the Local Communities of Polylofos, Myrtopotamia, Lefkochora, Avrami, Drakoneri, Analipsi, Karteroli, Moschorocholi, T Moschorochoi, P Lykotrafou of the new Municipality of Messina. In the implementation and execution of the above project was taken into account the coverage of the needs of the coastal zone of Messina – Analipsi


It is emphasized that the total budget of the entire project amounted to € 7,067,000.00 and was funded by the THESEAS & PEP program. PELOPONNESE – NSRF 2007 -2013

© 2020 Deyamessinis.gr. All Rights Reserved.

Web Design